(This is used by an individual to track how much time is spent on project activities.)
Group Number and Group Name | Project Description | Individual(s) Preparing | Review Date |
Legal Team | Project Firestorm | Norma Gleeson | 4/1/11 |
Task or subtask | Date | Hours worked | What’s going well? What’s not going well? Additional resources (people, technology) required? Are users and management participating? |
---|---|---|---|
Needs assessment conducted | 2/12/11 | 8 | Cross-functional team, including management. Requirements have been documented and agreed upon. |
Name search conducted, name approved | 2/14/11 | 4 | No issues. |
Real estate search conducted | 2/19/11 | 40 | Various properties researched and visited. |
Rental contract signed | 2/21/11 | 4 | Ahead of plan. |
Incorporation paperwork completed and filed | 2/21/11 | 40 | No issues. |
Incorporation status completed. | 3/3/11 | 16 | On target with plan. |
Investors contacted for funding opportunities | 3/31/11 | 36 | In process. |